The team only has 2 work days this week as thanksgiving is approaching. We held our team meeting as usual to discuss the remaining tasks that we have to complete:
- The design document of the prototype build due this Friday
- The handoff document should be finished by the end of this week
- Update the video based on the feedback from
- The shift of the festival format requires some adjustments as we need to stream the studio during the livestream
- Work on the final presentation slides and distribute
- Finish Archive and Post Modern stuffs
Beside the tasks listed above, team will double check the existing materials in the folder to make sure we deliver the product we promise.