The team only has 2 work days this week as thanksgiving is approaching. We held our team meeting as usual to discuss the remaining tasks that we have to complete:

  • The design document of the prototype build due this Friday
  • The handoff document should be finished by the end of this week
  • Update the video based on the feedback from 
  • The shift of the festival format requires some adjustments as we need to stream the studio during the livestream
  • Work on the final presentation slides and distribute
  • Finish Archive and Post Modern stuffs

Beside the tasks listed above, team will double check the existing materials in the folder to make sure we deliver the product we promise.

Comments are closed